Resolution
Suggestion to the documentListen to audioGet a link from a document element
of the Cabinet of ministers of the Republic of Uzbekistan
Suggestion to the documentListen to audioGet a link from a document element
On measures to improve the procedures for the examination of urban planning documents
Suggestion to the documentListen to audioGet a link from a document element
Suggestion to the documentListen to audioGet a link from a document element
In order to radically improve the system for the implementation of the examination of urban planning documents, further develop the activities of the subjects of urban planning activities related to the examination process by regulating their relationship on this matter, as well as ensuring transparency in the field through the full digitalization of expert procedural processes, the Cabinet of Ministers decrees following:
Suggestion to the documentListen to audioGet a link from a document element
1. Starting October 1, 2021, introduce a procedure according to which, during the examination of urban planning documents:
Suggestion to the documentListen to audioGet a link from a document element
consideration of urban planning documentation is carried out through the national information system “Transparent Construction” (hereinafter referred to as the information system) in accordance with the classification of objects by risk categories;
Suggestion to the documentListen to audioGet a link from a document element
project documentation of works carried out at the expense of external investment funds received within the state budget and sources equivalent to them, guarantees of the state and state organizations are reviewed by the State Unitary Enterprise “Shaharsozlik hujjatlari ekspertizasi” [“Expertise of urban planning documentation”] or its territorial branches;
Suggestion to the documentListen to audioGet a link from a document element
examination of design documentation for objects financed from other sources is carried out by accredited expert organizations – legal entities, State Unitary Enterprise “Shaharsozlik hujjatlari ekspertizasi” [“Expertise of urban planning documentation”] or its territorial branches according to the classification of risk categories of objects;
Suggestion to the documentListen to audioGet a link from a document element
a positive expert opinion on project documents is recognized as valid if it is entered in the “Unified Register of Expert Opinions” of the information system by an expert organization;
Suggestion to the documentListen to audioGet a link from a document element
a system will be introduced for calculating fees for services for the examination of urban planning documentation by expert organizations in a differentiated manner;
Suggestion to the documentListen to audioGet a link from a document element
specialists of expert organizations should be certified in the prescribed manner and a system of their certification will be established;
Suggestion to the documentListen to audioGet a link from a document element
develop and put into practice a methodology for using state statistics data on current prices for building materials, average prices for services of machines and mechanisms, average wages in preparing an expert opinion on the prices of resources used in the preparation of estimates for urban planning documentation
Suggestion to the documentListen to audioGet a link from a document element
2. Approve the Regulations on the procedure for the examination of design solutions for urban planning and design documentation for the construction, reconstruction, overhaul and current repairs of facilities in accordance with urban planning documentation in accordance with Appendix 1 .
Suggestion to the documentListen to audioGet a link from a document element
3. Approve the proposal of the Ministry of Construction of the Republic of Uzbekistan to strengthen the material and technical base of the State Unitary Enterprise “Shaharsozlik hujjatlari ekspertizasi” [“Expertise of urban planning documentation”] and its regional branches at the expense of the enterpriseʼs own funds.
Suggestion to the documentListen to audioGet a link from a document element
4. It should be noted that from October 1, 2021, the conclusion of the Ministry of Construction of the Republic of Uzbekistan on the prices of resources used in the estimate documentation for urban planning and design documentation will be formed using:
Suggestion to the documentListen to audioGet a link from a document element
the initial cost of facilities whose construction is financed from centralized sources, current prices for building materials, average prices for servicing machines and mechanisms, average wages, which are posted on the official website of the State Statistics Committee (stat.uz);
Suggestion to the documentListen to audioGet a link from a document element
at the same time, taking into account that prices change throughout the year, introduce a system of mutual settlements using statistical data on the average price increase for a certain period.
Suggestion to the documentListen to audioGet a link from a document element
5. The Ministry of Employment and Labor Relations of the Republic of Uzbekistan, together with the Ministry of Construction and the State Testing Center, within a month, in accordance with the established procedure, approve the regulation on the procedure for attestation and certification of experts involved in the examination of urban planning documentation.
Suggestion to the documentListen to audioGet a link from a document element
6. Ministry of Construction of the Republic of Uzbekistan should:
Suggestion to the documentListen to audioGet a link from a document element
until October 1, 2021, together with the Ministry of Development of Information Technologies and Communications, ensure the introduction of an improved system for the examination of urban planning documentation in the national information system "Transparent Construction";
Suggestion to the documentListen to audioGet a link from a document element
Until November 1, 2021, on the basis of a plan approved jointly with the State Testing Center, expert organizations must certify experts;
Suggestion to the documentListen to audioGet a link from a document element
Until November 10, 2021, together with the relevant ministries and departments, they must bring the legal documents they have adopted into line with this decision.
Suggestion to the documentListen to audioGet a link from a document element
7. The Ministry of Construction of the Republic of Uzbekistan, the State Statistics Committee, the State Tax Committee, the Ministry of Employment and Labor Relations, official ministries and departments, within two months, submit to the Cabinet of Ministers a draft document on the introduction of an electronic rating of expert organizations, generated automatically on the basis of statistical and departmental data.
Suggestion to the documentListen to audioGet a link from a document element
In order to further support and encourage expert organizations with the highest rating indicators, the draft document should provide for additional opportunities and benefits from the state.
Suggestion to the documentListen to audioGet a link from a document element
8. Approve the List of Resolutions of the Government of the Republic of Uzbekistan, recognized as invalid, in accordance with Appendix 2.
Suggestion to the documentListen to audioGet a link from a document element
9. Supervision of the execution of this Resolution shall be entrusted to the First Deputy Prime Minister of the Republic of Uzbekistan A.J. Ramatov and Minister of Construction of the Republic of Uzbekistan B.I. Zakirov.
Suggestion to the documentListen to audioGet a link from a document element
Prime Minister of the Republic of Uzbekistan A. ARIPOV
Suggestion to the documentListen to audioGet a link from a document element
Tashkent city,
Suggestion to the documentListen to audioGet a link from a document element
September 17, 2021 y.,
Suggestion to the documentListen to audioGet a link from a document element
No. 579
Suggestion to the documentListen to audioGet a link from a document element
Suggestion to the documentListen to audioGet a link from a document element
ANNEX 1
to the resolution of Cabinet of Ministers of the Republic of Uzbekistan of September17 , 2021, No. 579
Suggestion to the documentListen to audioGet a link from a document element
REGULATIONS
Suggestion to the documentListen to audioGet a link from a document element
on the procedure for the examination of design solutions for urban planning and design documentation for the construction, reconstruction, overhaul and current repairs of facilities in accordance with urban planning documentation
Suggestion to the documentListen to audioGet a link from a document element
Suggestion to the documentListen to audioGet a link from a document element
Chapter 1 General Provisions
Suggestion to the documentListen to audioGet a link from a document element
1. This Regulation applies to urban planning documents of legal and natural persons (hereinafter referred to as the customer), project documents developed for the construction, reconstruction, overhaul and current repair, modernization, re-equipment of buildings, structures and other objects (working project , project-estimate documents, working documents) from the examination of the compliance with the requirements of legislative documents on urban development, earthquake resistance, engineering studies, energy efficiency indicators, fire protection and environmental norms and regulations, sanitary rules and norms, hygiene norms determines the transfer procedure.
Suggestion to the documentListen to audioGet a link from a document element
2. The Regulation uses the following fundamental concepts:
Suggestion to the documentListen to audioGet a link from a document element
expert – a highly educated specialist who has passed attestation in the prescribed manner and has an appropriate certificate, has at least five years of work experience in the construction industry (mainly worked in project organizations);
Suggestion to the documentListen to audioGet a link from a document element
feasibility study (hereinafter - FS) – the most effective technical method of project implementation based on the study of alternative options, which determines the total maximum value of the project and the size of the financing need, taking into account the considered initial conditions of financing pre-project documents justifying the choice of technological and organizational solution;
Suggestion to the documentListen to audioGet a link from a document element
working design (hereinafter – WD) – a design document consisting of a technical design prepared together with the approved part and working drawings, which are the main technical and economic indicators, and working documents that reflect the greatest value;
Suggestion to the documentListen to audioGet a link from a document element
working documents – a project document consisting of a collection of working drawings for individual buildings and structures and types of work. When drawing up working documentation for complex objects, along with working drawings developed for the entire building and structure, additional studies are carried out on the defining materials of the project. Changes in the cost of man-hours and basic building materials should be included in the working documentation, specifications, dimensional diagrams for the relevant types of equipment and products, passports of working construction drawings of buildings and structures should be drawn up. As a rule, working documents are developed on the basis of a feasibility study approved in the prescribed manner;
Suggestion to the documentListen to audioGet a link from a document element
network scientific and technical council (hereinafter – NSTC) – in order to determine the main technical and technological solutions of the project in terms of its compatibility with the prospects for the development of the network, taking into account the directions for the introduction of advanced technologies, deep processing of local raw materials by a collegiate body established by the decision of the initiator (customer);
Suggestion to the documentListen to audioGet a link from a document element
urban planning documents – approved documents for planning the development of districts and settlements in terms of urban planning and their development.
Suggestion to the documentListen to audioGet a link from a document element
3. Examination of urban planning documentation is carried out by specialized structural divisions of a specially authorized state body, specialized structural divisions of competent ministries, committees and departments, expert commissions and groups, as well as accredited legal entities (hereinafter referred to as expert organizations).
Suggestion to the documentListen to audioGet a link from a document element
Examination of urban planning documentation of separately regulated objects of urban planning activities is carried out by specialized structural divisions of a specially authorized state body.
Suggestion to the documentListen to audioGet a link from a document element
4. Urban planning documents are subject to examination for compliance with the requirements of legal documents on urban planning, seismic resistance, engineering surveys, fire and environmental standards and rules, sanitary rules and regulations, hygiene rules.
Suggestion to the documentListen to audioGet a link from a document element
5. For the construction of urban planning objects, the technical part of the projects of urban planning documentation is subject to mandatory expertise, i.e., seismic resistance, energy efficiency indicators, fire safety.
Suggestion to the documentListen to audioGet a link from a document element
6. For all construction objects, an examination of the estimated part of the projects is mandatory, with the exception of objects, the construction of which is carried out at the expense of direct investments, including foreign ones.
Suggestion to the documentListen to audioGet a link from a document element
7. Examination of design documentation for the following facilities is not mandatory:
Suggestion to the documentListen to audioGet a link from a document element
temporary and outbuildings for seasonal work;
Suggestion to the documentListen to audioGet a link from a document element
small-sized facilities under construction with a volume of no more than three hundred cubic meters;
Suggestion to the documentListen to audioGet a link from a document element
single-apartment residential buildings with a height of no more than two floors (excluding the basement), a height of 12 meters above the ground and (or) a total area of not more than 500 square meters;
Suggestion to the documentListen to audioGet a link from a document element
buildings and structures under current repair.
Suggestion to the documentListen to audioGet a link from a document element
8. Experts and expert organizations are independent in their activities from the subjects of urban planning. No one has the right to interfere in the work of experts or expert organizations when considering urban planning documents and preparing expert opinions on them.
Suggestion to the documentListen to audioGet a link from a document element
9. A positive expert opinion on project documents is recognized as valid if it is included in the “Unified Register of Expert Opinions” in the national information system “Transparent Construction” (hereinafter referred to as the information system) by expert organizations, with the exception of the examination of project documents containing information constituting a state secret.
Suggestion to the documentListen to audioGet a link from a document element
10. Expert organizations and experts, in their activities are guided by the Constitution and laws of the Republic of Uzbekistan, decrees of the chambers of the Oliy Majlis of the Republic of Uzbekistan, decrees, resolutions and orders of the President of the Republic of Uzbekistan, decrees and orders of the Cabinet of Ministers of the Republic of Uzbekistan, as well as this Regulation and other legislative acts.
Suggestion to the documentListen to audioGet a link from a document element
11. Expert opinion on the prices of resources used in the assessment of urban planning and design documentation:
Suggestion to the documentListen to audioGet a link from a document element
the initial cost of facilities, the construction of which is financed from centralized sources, is formed using the current prices for building materials posted on the official website of the State Statistics Committee (stat.uz), average prices for servicing machines and mechanisms and average wages;
Suggestion to the documentListen to audioGet a link from a document element
taking into account price changes during the year, the average price for a certain period is calculated using statistical data on price increases.
Suggestion to the documentListen to audioGet a link from a document element
Chapter 2 Tasks, functions, rights and obligations of expert organizations
Suggestion to the documentListen to audioGet a link from a document element
12. Within their powers, expert organizations perform the following tasks:
Suggestion to the documentListen to audioGet a link from a document element
a) ensure the organization and conduct of the examination of urban planning documentation in the prescribed manner;
Suggestion to the documentListen to audioGet a link from a document element
b) consideration of disputes between customers, developers of urban planning documentation and other organizations in the field of urban planning activities;
Suggestion to the documentListen to audioGet a link from a document element
c) examination of master plans for cities and urban-type settlements, as well as architectural and planning projects for the territories of rural (village) gatherings of citizens;
Suggestion to the documentListen to audioGet a link from a document element
d) advanced training of personnel, their retraining, training and certification in advanced foreign countries;
Suggestion to the documentListen to audioGet a link from a document element
e) control measurements in construction.
Suggestion to the documentListen to audioGet a link from a document element
13. Expert organizations perform the following functions in the performance of the tasks assigned to them:
Suggestion to the documentListen to audioGet a link from a document element
a) in the field of ensuring the organization and examination of urban planning documents in the prescribed manner:
Suggestion to the documentListen to audioGet a link from a document element
conducts an examination for compliance of projects of objects with urban planning, earthquake resistance, engineering surveys, fire and environmental standards and rules, sanitary rules and standards, hygiene rules;
Suggestion to the documentListen to audioGet a link from a document element
attracts, on the basis of a contract, specialists in urban planning, seismic resistance, engineering surveys, compliance with fire and environmental standards and rules, sanitary rules and regulations, sanitary and hygienic rules;
Suggestion to the documentListen to audioGet a link from a document element
monitors the conclusions of expert organizations on a quarterly basis and at the end of the year;
Suggestion to the documentListen to audioGet a link from a document element
uploads expert opinions to the information system;
Suggestion to the documentListen to audioGet a link from a document element
b) in the field of dispute resolution between customers, developers of urban planning documentation and other organizations in the field of urban planning activities:
Suggestion to the documentListen to audioGet a link from a document element
considers disputes between customers, developers of urban planning documentation, contractors and other organizations at their request;
Suggestion to the documentListen to audioGet a link from a document element
gives appropriate conclusions regarding disagreements;
Suggestion to the documentListen to audioGet a link from a document element
submits to a specially authorized body a report on design organizations that have made gross shortcomings and errors in design;
Suggestion to the documentListen to audioGet a link from a document element
c) in the field of examination of master plans for cities and urban-type settlements, as well as architectural and planning projects for the territories of settlements (villages) by citizensʼ gatherings:
Suggestion to the documentListen to audioGet a link from a document element
within its powers, conducts an examination of master plans for cities and urban-type settlements, as well as architectural and planning projects for the territories of settlements (villages);
Suggestion to the documentListen to audioGet a link from a document element
within the limits of its authority, when conducting an examination of master plans for cities and urban-type settlements, architectural and planning projects of settlements (villages) in terms of urban planning, compliance with urban planning, seismic resistance, engineering surveys, fire inspection of combat and environmental standards and rules, sanitary rules and norms , hygiene standards;
Suggestion to the documentListen to audioGet a link from a document element
evaluates the quality of the performed design and survey work;
Suggestion to the documentListen to audioGet a link from a document element
d) in the field of advanced training of personnel, their retraining, training and certification in advanced foreign countries:
Suggestion to the documentListen to audioGet a link from a document element
constantly improves the qualifications of the staff;
Suggestion to the documentListen to audioGet a link from a document element
takes measures to train, retrain and improve the skills of specialists in foreign developed countries;
Suggestion to the documentListen to audioGet a link from a document element
provides certification of experts in accordance with the established procedure;
Suggestion to the documentListen to audioGet a link from a document element
ensures that the experts pass the certification in a timely manner;
Suggestion to the documentListen to audioGet a link from a document element
e) in the field of control measurements in construction:
Suggestion to the documentListen to audioGet a link from a document element
checks the completeness and correctness of the preparation of urban planning documentation and reports for the construction site;
Suggestion to the documentListen to audioGet a link from a document element
measures the volume of actually performed physical work at the construction site on the basis of project documents, proposals and invoices for the work performed;
Suggestion to the documentListen to audioGet a link from a document element
based on the results of the control measure by type of work, it is determined whether the types of work provided for in the project documents, offer and reports are actually being carried out;
Suggestion to the documentListen to audioGet a link from a document element
shows deviations from the project in the amount of actually performed work at the construction site as a result of the control measure;
Suggestion to the documentListen to audioGet a link from a document element
checks the use of dimensions, calculation, technical parameters and quality of building materials at construction sites on the basis of a mutual official agreement, contract, offer, project documents and reports between the customer and the contractor;
Suggestion to the documentListen to audioGet a link from a document element
checks whether the tests of equipment and communication systems reflected in the reports were really carried out;
Suggestion to the documentListen to audioGet a link from a document element
ensures the confidentiality of the results of control measurements;
Suggestion to the documentListen to audioGet a link from a document element
checks reports for arithmetic errors and other calculations.
Suggestion to the documentListen to audioGet a link from a document element
14. Expert organizations have the following rights:
Suggestion to the documentListen to audioGet a link from a document element
verification of the compliance of the adopted architectural, planning and urban planning decisions with urban planning norms and rules;
Suggestion to the documentListen to audioGet a link from a document element
verification of compliance with the mandatory requirements of urban planning norms and rules, mandatory requirements for the use of energy-efficient and energy-saving technical, technological and innovative design solutions;
Suggestion to the documentListen to audioGet a link from a document element
providing an opinion on the results of the examination;
Suggestion to the documentListen to audioGet a link from a document element
to assess the quality of the performed design and survey work.
Suggestion to the documentListen to audioGet a link from a document element
Expert organizations may also have other rights in accordance with the law.
Suggestion to the documentListen to audioGet a link from a document element
15. Experts have the following rights:
Suggestion to the documentListen to audioGet a link from a document element
participation in expert commissions (expert groups) for comprehensive urban planning expertise of regional urban planning projects;
Suggestion to the documentListen to audioGet a link from a document element
request and receive the necessary materials and information from customers and developers;
Suggestion to the documentListen to audioGet a link from a document element
in accordance with the professional specialization of urban planning activities, conducting expert examinations for individual departments (parts) of projects, drawing up local expert opinions on them. Local expert opinions for individual departments (parts) are not considered the basis for the general approval of urban planning documentation and are used to draw up a consolidated expert opinion;
Suggestion to the documentListen to audioGet a link from a document element
in cases of non-compliance by the customer with the conditions (requirements) specified in the expert opinion, offer to withdraw the expert opinion previously issued by the expert organization.
Suggestion to the documentListen to audioGet a link from a document element
Experts may have other rights in accordance with the law.
Suggestion to the documentListen to audioGet a link from a document element
16. Expert Responsibilities:
Suggestion to the documentListen to audioGet a link from a document element
ensuring observance and safety of state secrets and other secrets protected by law in relation to the considered projects of urban planning documents;
Suggestion to the documentListen to audioGet a link from a document element
improving professional skills;
Suggestion to the documentListen to audioGet a link from a document element
must comply with the rules of professional ethics.
Suggestion to the documentListen to audioGet a link from a document element
Experts may also have other responsibilities.
Suggestion to the documentListen to audioGet a link from a document element
17. Experts are prohibited from:
Suggestion to the documentListen to audioGet a link from a document element
conducting an examination of projects directly or indirectly involved in the preparation of this examination, or projects carried out with the participation of a husband (wife) and (or) other close relatives;
Suggestion to the documentListen to audioGet a link from a document element
be in labor, financial and (or) other subordinate relations with the subjects of urban planning activities.
Suggestion to the documentListen to audioGet a link from a document element
Chapter 3 The procedure for submitting and considering urban planning documentation to expert organizations
Suggestion to the documentListen to audioGet a link from a document element
18. The procedure for the submission and consideration of urban planning documents to expert organizations through the national information system “"Transparent Construction” is carried out in accordance with Appendix 1 to this Regulations.
Suggestion to the documentListen to audioGet a link from a document element
19. The customer submits an application for the examination of urban planning documentation through the information system in electronic form through the information system to expert organizations in the following order:
Suggestion to the documentListen to audioGet a link from a document element
а) for new construction – in accordance with Appendix 2 to this Regulation;
Suggestion to the documentListen to audioGet a link from a document element
b) for reconstruction – in accordance with Appendix 3 to this Regulation;
Suggestion to the documentListen to audioGet a link from a document element
c) for a major overhaul – in accordance with Appendix 4 to this Regulation;
Suggestion to the documentListen to audioGet a link from a document element
г) for current repair work– in accordance with Appendix 5 to this Regulation.
Suggestion to the documentListen to audioGet a link from a document element
20. Urban planning documentation is reviewed through the information system in accordance with the classification of objects by risk categories.
Suggestion to the documentListen to audioGet a link from a document element
21. Project documentation for works performed at the expense of foreign investment funds received under the guarantees of the state budget and equivalent sources, government organizations and non-governmental organizations are reviewed by the SUE “Shaharsozlik hujjatlari ekspertizasi” [“Expertise of urban planning documentation”] or its territorial branches. Project documentation for objects financed from other sources is subject to expert examination by expert organizations at the voluntary request of the customer.
Suggestion to the documentListen to audioGet a link from a document element
22. Expertise of urban planning documentation is considered by risk categories in the following order:
Suggestion to the documentListen to audioGet a link from a document element
Objects of the 1st category – examination of project documentation is not required;
Suggestion to the documentListen to audioGet a link from a document element
Objects of category II – examination of project documentation is carried out by expert organizations at the discretion of the customer in accordance with paragraph 21 of this Regulation;
Suggestion to the documentListen to audioGet a link from a document element
Objects of category III – project documents submitted by the customer through the information system are sent to the SUE “Shaharsozlik hujjatlari ekspertizasi”. These documents can be sent to regional offices or expert organizations of the SUE “Shaharsozlik hujjatlari ekspertizasi” or reviewed by itself;
Suggestion to the documentListen to audioGet a link from a document element
Objects with an attendance of 5,000 or more people (including large shopping malls) undergo an examination by the SUE “Shaharsozlik hujjatlari ekspertizasi” or its regional branches;
Suggestion to the documentListen to audioGet a link from a document element
Objects of category IV – project documents are reviewd only by the SUE “Shaharsozlik hujjatlari ekspertizasi”.
Suggestion to the documentListen to audioGet a link from a document element
23. Pre-project documents (feasibility studies) of objects implemented at the expense of investment funds and projects under import contracts are subject to examination by the SUE “Loyihalarni va import kontraktlarni kompleks ekspertiza qilish markazi” [“Center for Comprehensive Expertise of Projects and Import Contracts”] under the Ministry of Economic Development and Poverty Reduction under a separate procedure.
Suggestion to the documentListen to audioGet a link from a document element
24. The corresponding application sent by the customer through the information system will be checked by an expert organization within three working days.
Suggestion to the documentListen to audioGet a link from a document element
If, as a result of the verification, the urban planning documents are incomplete or the attached documents do not meet the specified requirements, the expert organization notifies the customer through the information system about the elimination of the identified deficiencies within five working days.
Suggestion to the documentListen to audioGet a link from a document element
From the date of receipt of the relevant request from the expert organization about the identified deficiencies, the customer, within ten working days, submits the relevant documents to the expert organization through the information system.
Suggestion to the documentListen to audioGet a link from a document element
25. Copies of positive conclusions issued by expert organizations must be electronically uploaded to the program “Expertise of project documents” of the information system.
Suggestion to the documentListen to audioGet a link from a document element
Project documents of separate and important objects are excluded.
Suggestion to the documentListen to audioGet a link from a document element
26. In accordance with the relevant documents, an expert opinion on objects carried out simultaneously with construction work is issued through the information system in stages and to the extent according to the schedule specified in the expert agreement.
Suggestion to the documentListen to audioGet a link from a document element
27. Expert organizations prepare a consolidated expert opinion on urban planning documents, taking into account expert (industry) opinions of independent experts (expert groups) involved in the consideration of urban planning documents.
Suggestion to the documentListen to audioGet a link from a document element
28. The consolidated expert opinion, drawn up based on the results of the examination of urban planning documentation, is signed by the expert and approved by the head of the expert organization, and the expert opinion given in the prescribed manner is sent to the customer.
Suggestion to the documentListen to audioGet a link from a document element
29. The customer and the design organization are responsible for the quality of urban planning documents submitted to the expert organization, the reliability of the initial data and the adopted design decisions.
Suggestion to the documentListen to audioGet a link from a document element
Chapter 4 Expert cost of urban planning documents
Suggestion to the documentListen to audioGet a link from a document element
30. Examination of urban planning documentation is carried out on the basis of an agreement between the customer and expert organizations.
Suggestion to the documentListen to audioGet a link from a document element
After making a 100% prepayment in accordance with the agreements concluded with the SUE “Shaharsozlik hujjatlari ekspertizasi” and its regional branches, an expert opinion on urban planning and design documentation will be submitted.
Suggestion to the documentListen to audioGet a link from a document element
At the same time, an advance payment in the amount of 30 percent is paid by the customer in the process of input (unloading) of design and estimate documentation through the electronic system.
Suggestion to the documentListen to audioGet a link from a document element
The amount of the advance in contracts for the examination of urban planning documentation of accredited legal entities is determined in accordance with the law.
Suggestion to the documentListen to audioGet a link from a document element
31. The cost of premises for domestically produced equipment is reflected in the expertise summary.
Suggestion to the documentListen to audioGet a link from a document element
32. Prices for objects, the construction of which was carried out simultaneously with the design documentation, are calculated based on the prices prevailing on the ground, on the basis of a price offer agreed between the customer and the contractor.
Suggestion to the documentListen to audioGet a link from a document element
33. The fee for the examination of urban planning documentation by expert organizations is calculated in accordance with Appendix 6 to this Regulation.
Suggestion to the documentListen to audioGet a link from a document element
Chapter 5 Terms for consideration of urban planning documentation
Suggestion to the documentListen to audioGet a link from a document element
34. By risk category:
Suggestion to the documentListen to audioGet a link from a document element
Examination of urban planning documentation of objects of category I will be considered within fifteen days;
Suggestion to the documentListen to audioGet a link from a document element
Expertise of urban planning documentation of objects of II, III and IV categories will be considered within thirty days.
Suggestion to the documentListen to audioGet a link from a document element
35. Based on the volume and complexity of urban planning documentation, the terms of the examination can be extended by agreement of the parties.
Suggestion to the documentListen to audioGet a link from a document element
36. The period of validity of expert opinions issued by expert organizations for urban planning documents is 2 years.
Suggestion to the documentListen to audioGet a link from a document element
Chapter 6 Expert opinion
Suggestion to the documentListen to audioGet a link from a document element
37. The expert opinion should include:
Suggestion to the documentListen to audioGet a link from a document element
a brief description of information about the conditions for the implementation of construction and the main design decisions and sources of technical and economic indicators of the construction object;
Suggestion to the documentListen to audioGet a link from a document element
specific comments and suggestions on changes and additions to urban planning documents regarding the design decisions adopted during the examination;
Suggestion to the documentListen to audioGet a link from a document element
recommendations for additional detailed refinement of individual design solutions during the subsequent design process;
Suggestion to the documentListen to audioGet a link from a document element
description of the project of the object in accordance with urban planning norms and rules;
Suggestion to the documentListen to audioGet a link from a document element
a conclusion indicating the reasons for the recommendations given for the approval of urban planning documentation (in the absence of serious objections leading to a change in design decisions and main technical and economic indicators) or rejection (return for revision).
Suggestion to the documentListen to audioGet a link from a document element
38. The results of the examination are considered to be a consolidated expert opinion, which reflects:
Suggestion to the documentListen to audioGet a link from a document element
requirements that urban planning documents meet the established requirements and be recommended for further consideration and approval;
Suggestion to the documentListen to audioGet a link from a document element
the marginal cost of construction objects, with the exception of the cost of objects, the construction of which is carried out at the expense of direct investment, including foreign investment;
Suggestion to the documentListen to audioGet a link from a document element
non-compliance of urban planning documentation with the established requirements, applications for rejection or return for reconsideration.
Suggestion to the documentListen to audioGet a link from a document element
39. A positive conclusion of the expertise of urban planning documentation is the basis for:
Suggestion to the documentListen to audioGet a link from a document element
approval of urban planning documentation in the prescribed manner;
Suggestion to the documentListen to audioGet a link from a document element
development of the next design stage;
Suggestion to the documentListen to audioGet a link from a document element
registration of an object in the field of construction in the regional control inspection;
Suggestion to the documentListen to audioGet a link from a document element
preparation of tender documentation;
Suggestion to the documentListen to audioGet a link from a document element
make funding.
Suggestion to the documentListen to audioGet a link from a document element
40. A sample form of an expert opinion of an urban planning document is drawn up in accordance with Appendix 7 to this Regulation.
Suggestion to the documentListen to audioGet a link from a document element
41. The conclusion is drawn up in two copies, one copy remains with the customer, the second - with the expert organization.
Suggestion to the documentListen to audioGet a link from a document element
Chapter 7 Final Provisions
Suggestion to the documentListen to audioGet a link from a document element
42. In case of changes in design solutions, including changes in the design of objects under construction or existing (there are changes that affect the seismic resistance of the building and fire safety), a re-examination of urban planning documentation is carried out in terms of the changes made.
Suggestion to the documentListen to audioGet a link from a document element
43. The conclusions of expert organizations may be appealed in accordance with the procedure established by law in relation to illegal actions (inaction) of their officials.
Suggestion to the documentListen to audioGet a link from a document element
44. If officials detect errors or cases of low-quality expertise at least three times during the year, according to the information and indicators specified in the conclusions issued by a certain expert organization, a document (certificate) is drawn up authorizing the expert organization to conduct an expertise will be canceled by the competent authority and will be deprived of the right to engage in this activity for three years.
Suggestion to the documentListen to audioGet a link from a document element
In case of poor-quality expertise, experts and expert organizations will bear responsibility in accordance with legal acts.
Suggestion to the documentListen to audioGet a link from a document element
45. Persons guilty of violating the requirements of this Regulation are liable in the manner prescribed by law.
Suggestion to the documentListen to audioGet a link from a document element
Suggestion to the documentListen to audioGet a link from a document element
APPENDIX 1
to the Regulation on the procedure for the examination of design solutions for urban planning and design documentation for the construction, reconstruction, overhaul and current repairs of facilities in accordance with urban planning documentation
Suggestion to the documentListen to audioGet a link from a document element
PROCEDURE
Suggestion to the documentListen to audioGet a link from a document element
for submitting and reviewing urban planning documentation to expert organizations through the national information system “Transparent Construction”
Suggestion to the documentListen to audioGet a link from a document element
Suggestion to the documentListen to audioGet a link from a document element

Phases

Responsible person

Measures

Deadlines

Phase 1

Customer

Submission of urban planning documentation to the expert organization through the national information system

According to established order

Phase 2

Automatically by the information system

Acceptance of the received application for the examination of urban planning documentation and sending it to the head for the formation of the assignment.

within 1 day

Phase 3

Head of the expert organization

Sending an electronic application for the examination of urban planning documentation for consideration by the chief expert.

within 1 day

Phase 4

Chief Expert

After having studied the completeness of urban planning documentation:

1. If the documents are submitted in full, send to the contract department for the preparation of the contract for examination;

within 1 day

2. According to the results of the study, in case of incompleteness of urban planning documents or non-compliance of the attached documents with the established requirements, return them to the customer to eliminate the identified deficiencies.

within 5 day

Phase 5

Customer

From the date of receipt of the relevant request of the expert organization about the shortcomings identified in the urban planning documentation, the direction to the expert organization of the relevant documents on the elimination of these shortcomings.

within 10 day

Phase 6

Department of Contracts of the expert organization

Preparation of a contract for the examination of urban planning documentation and sending to the customer.

within 1 day

Phase 7

Customer

Payment of the fee calculated under the contract for the examination of urban planning documentation to the settlement account of the expert organization.

within 3 day

Phase 8

Department of Contracts of the expert organization

Sending a payment notice to the chief expert about payment by the customer for the examination of urban planning documentation.

 

within 1 day

Phase 9

Chief Expert

Sending an application for the examination of urban planning documentation to the relevant experts with a set deadline.

within 1 day

Phase 10

Experts

1. Examination of urban planning documents in the prescribed manner.

2. Entering conclusions on the results of the examination into the information system and sending them to the chief expert for the preparation of a consolidated expert opinion.

within 12 day

Phase 11

Chief Expert

1. Studying the conclusions presented by the experts and preparing a consolidated expert opinion on their basis.

2. Sending the collective expert opinion for approval to the head of the expert organization.

within 12 day

Phase 12

Head of the expert organization

1. Confirmation of the consolidated expert opinion with own electronic digital signature and forwarding to the customer.

2. Placement of a collective expert opinion in the Unified Electronic Register in the information system.

within 1 day

Suggestion to the documentListen to audioGet a link from a document element
Suggestion to the documentListen to audioGet a link from a document element
APPENDIX 2
to the Regulation on the procedure for the examination of design solutions for urban planning and design documentation for the construction, reconstruction, overhaul and current repairs of facilities in accordance with urban planning documentation
Suggestion to the documentListen to audioGet a link from a document element
APPLICATION FORM
Suggestion to the documentListen to audioGet a link from a document element
for the examination of urban planning documentation for new construction through the information system
Suggestion to the documentListen to audioGet a link from a document element
Suggestion to the documentListen to audioGet a link from a document element

On company letterhead

To _____________________________(name of the Expert organization)

From __________________________(name of the customer (project developer)

Legal address, company code, IBAN, bank account

APPLICATION

1. Regulatory document, which is the basis for the new construction of the facility:

_______________________________________________________________ (Decrees, decisions and instructions of the President of the Republic of Uzbekistan, resolutions, instructions and other documents of the Cabinet of Ministers)

2. Architectural and planning task approved by the Ministry of Construction of the Republic of Karakalpakstan, regions or main construction departments of Tashkent city:

______________________________________________________________________

(statement, year, month, day)

3. Design task approved by the authorities in the prescribed manner:

________________________________________________________________________

4. Specifications for connection to engineering networks, materials agreed with interested organizations that control and operate engineering networks:

______________________________________________________________________

5. Conclusions based on the results of engineering and geological surveys of the construction site:

______________________________________________________________________

6. A contract for the execution of design and survey work was concluded:

______________________________________________________________________

(copy ofcontract)

7. Design license:

______________________________________________________________________

(license number, year, month, day of issue)

8. Conclusion of the Council adopted by the Ministry of Construction of the Republic of Karakalpakstan, regions or main construction departments of the city of Tashkent in the area where the facility is located:

______________________________________________________________________

(issued year, month, day)

9. The indisputable conclusion of the regional bodies of the State Committee for Ecology and Environmental Protection:

______________________________________________________________________

(at the request of the expert organization, in appropriate cases)

10. Materials and documents reviewed and approved at the previous design stage:

______________________________________________________________________

(at the request of the expert organization, in appropriate cases)

11. Conclusion (summary) of the research council of the specially authorized body:

______________________________________________________________________

(at the request of the expert organization, in appropriate cases for especially important, special or strategic facilities)

12. Industry Findings:

______________________________________________________________________

(at the request of the expert organization, in appropriate cases)

______________________________________________________________________

Suggestion to the documentListen to audioGet a link from a document element
Note: The requirements under paragraphs 1-9 are mandatory, if the documents under paragraphs 10-13 are not submitted by the customer, they must be submitted based on the request of the expert organization.
Suggestion to the documentListen to audioGet a link from a document element
Suggestion to the documentListen to audioGet a link from a document element
APPENDIX 3
to the Regulation on the procedure for the examination of design solutions for urban planning and design documentation for the construction, reconstruction, overhaul and current repairs of facilities in accordance with urban planning documentation
Suggestion to the documentListen to audioGet a link from a document element
APPLICATION FORM
Suggestion to the documentListen to audioGet a link from a document element
for the examination of urban planning documentation for the reconstruction of objects through the information system
Suggestion to the documentListen to audioGet a link from a document element
Suggestion to the documentListen to audioGet a link from a document element

On company letterhead

To _____________________________(name of the Expert organization)

From __________________________(name of the customer (project developer)

Legal address, company code, IBAN, bank account

APPLICATION

1. Regulatory document, which is the basis for the reconstruction of the facility:

___________________________________________________________________________

(Decrees, decisions and instructions of the President of the Republic of Uzbekistan, resolutions, instructions and other documents of the Cabinet of Ministers)

2. Architectural and planning task approved by the Ministry of Construction of the Republic of Karakalpakstan, regions or main construction departments of Tashkent city:

____________________________________________________________________________

(statement, year, month, day)

3. Design task approved by the authorities in the prescribed manner:

____________________________________________________________________________

4. Specifications for connection to engineering networks, materials agreed with interested organizations that control and operate engineering networks:

___________________________________________________________________________

5. Conclusions based on the results of engineering and geological surveys of the construction site:

____________________________________________________________________________

6. Conclusion on the technical inspection of buildings and structures requiring reconstruction:

____________________________________________________________________________

7. A contract for the execution of design and survey work was concluded:

____________________________________________________________________________

(copy of contract)

8. Design license:

____________________________________________________________________________

(license number, year, month, day of issue)

9. Defect detection statement

___________________________________________________________________________

10. Conclusion of the Council adopted by the Ministry of Construction of the Republic of Karakalpakstan, regions or main construction departments of the city of Tashkent in the area where the facility is located:

____________________________________________________________________________

(issued on dd/mm/yyyy)

11. The indisputable conclusion of the regional bodies of the State Committee for Ecology and Environmental Protection:

___________________________________________________________________________

(at the request of the expert organization, in appropriate cases)

 

12. Materials and documents reviewed and approved at the previous design stage:

___________________________________________________________________________

(at the request of the expert organization, in appropriate cases)

13. Conclusion (summary) of the research council of the specially authorized body:

___________________________________________________________________________

(at the request of the expert organization, in appropriate cases for especially important, special or strategic facilities)

14. Industry Findings:

__________________________________________________________________________

(at the request of the expert organization, in appropriate cases)

__________________________________________________________________________

Suggestion to the documentListen to audioGet a link from a document element
Note: The requirements under paragraphs 1-7 are mandatory, if the documents under paragraphs 8-14 are not submitted by the customer, they must be submitted based on the request of the expert organization.
Suggestion to the documentListen to audioGet a link from a document element
Suggestion to the documentListen to audioGet a link from a document element
APPENDIX 4
to the Regulation on the procedure for the examination of design solutions for urban planning and design documentation for the construction, reconstruction, overhaul and current repairs of facilities in accordance with urban planning documentation
Suggestion to the documentListen to audioGet a link from a document element
APPLICATION FORM
Suggestion to the documentListen to audioGet a link from a document element
for the examination of urban planning documentation for the overhaul of objects through the information system
Suggestion to the documentListen to audioGet a link from a document element
Suggestion to the documentListen to audioGet a link from a document element

On company letterhead

To _____________________________(name of the Expert organization)

From __________________________

(name of the customer (project developer)

Legal address, company code, IBAN, bank account

APPLICATION

1. Regulatory document, which is the basis for the overhaul of the facility:

______________________________________________________________________

(Decrees, decisions and instructions of the President of the Republic of Uzbekistan, resolutions, instructions and other documents of the Cabinet of Ministers)

2. Design task approved by the authorities in the prescribed manner:

______________________________________________________________________

3. A contract for the execution of design and survey work was concluded:

______________________________________________________________________

(copy of contract)

4. Design license:

______________________________________________________________________

(license number, year, month, day of issue)

5. Defect detection statement

______________________________________________________________________

6. Conclusion on the technical inspection of buildings and structures requiring major repairs:

______________________________________________________________________

7. Conclusion of the Council adopted by the Ministry of Construction of the Republic of Karakalpakstan, regions or main construction departments of the city of Tashkent in the area where the facility is located:

______________________________________________________________________

(issued year, month, day)

8. Industry Findings:

______________________________________________________________________

(at the request of the expert organization, in appropriate cases)

Suggestion to the documentListen to audioGet a link from a document element
Note: The requirements under paragraphs 1-7 are mandatory, if the documents under paragraph 8 are not submitted by the customer, they must be submitted based on the request of the expert organization.
Suggestion to the documentListen to audioGet a link from a document element
Suggestion to the documentListen to audioGet a link from a document element
APPENDIX 5
to the Regulation on the procedure for the examination of design solutions for urban planning and design documentation for the construction, reconstruction, overhaul and current repairs of facilities in accordance with urban planning documentation
Suggestion to the documentListen to audioGet a link from a document element
for the examination of urban planning documentation for the maintenance of objects through the information system
Suggestion to the documentListen to audioGet a link from a document element
APPLICATION FORM
Suggestion to the documentListen to audioGet a link from a document element
Suggestion to the documentListen to audioGet a link from a document element

On company letterhead

To _____________________________(name of the Expert organization)

From __________________________

(name of the customer (project developer)

Legal address, company code, IBAN, bank account

APPLICATION

1. Regulatory document, which is the basis for the overhaul of the facility:

______________________________________________________________________

(Decrees, decisions and instructions of the President of the Republic of Uzbekistan, resolutions, instructions and other documents of the Cabinet of Ministers)

2. Design task approved by the authorities in the prescribed manner:

______________________________________________________________________

3. A contract for the execution of design and survey work was concluded:

______________________________________________________________________

(copy of contract)

4. Design license:

______________________________________________________________________

(license number, year, month, day of issue)

5. Defect detection statement

______________________________________________________________________

Suggestion to the documentListen to audioGet a link from a document element
Note: The requirements for points 1-5 are mandatory.
Suggestion to the documentListen to audioGet a link from a document element
Suggestion to the documentListen to audioGet a link from a document element
APPENDIX 6
to the Regulation on the procedure for the examination of design solutions for urban planning and design documentation for the construction, reconstruction, overhaul and current repairs of facilities in accordance with urban planning documentation
Suggestion to the documentListen to audioGet a link from a document element
TABLE FOR CALCULATING
Suggestion to the documentListen to audioGet a link from a document element
the cost of services of the SUE “Shaharsozlik hujjatlari ekspertizasi” and its regional branches, accredited legal entities, for the examination of urban planning documentation
Suggestion to the documentListen to audioGet a link from a document element
Suggestion to the documentListen to audioGet a link from a document element

#

Name of the examination of works to be performed

Base

Unit

Share of estimated cost

1.

Examination of design and estimate documentation for new construction, reconstruction and overhaul *

from the estimated cost

%

0.1

2.

Expert review of the revision of design estimates for new construction, reconstruction and overhaul projects*

from the estimated cost

%

0.05

3.

Examination of the estimated cost of all objects **

from the estimated cost

%

0.05

4.

Examination of the estimated cost for the revision of all objects**

from the estimated cost

%

0.02

5.

Conclusions of the examination of seismic resistance and fire safety of projects of objects***

2% of Basic calculated value of working volume (m2)

1.5% of Basic calculated value of working volume (m3)

1% of Basic calculated value of working volume (meter of run)

6.

Involvement of specialists from law enforcement and other bodies as experts

5 times the base calculated value for each day

Suggestion to the documentListen to audioGet a link from a document element
Note:
Suggestion to the documentListen to audioGet a link from a document element
Verification of the contractorʼs other costs, mechanized costs and other work calculations is not considered mandatory, and the service fee is calculated in the amount of at least 2 times the base calculated value.
Suggestion to the documentListen to audioGet a link from a document element
* The service of a full examination of design and estimate documentation is determined by at least 3 times the base calculated value.
Suggestion to the documentListen to audioGet a link from a document element
** The minimum amount charged for the examination of the appraised value of objects is equal to 2 times the amount of the base calculated value.
Suggestion to the documentListen to audioGet a link from a document element
*** When calculating the contractual cost of objects, along with the volume of construction, the volumes of the basement, floors and superstructures, structures, engineering and communication networks are taken into account.
Suggestion to the documentListen to audioGet a link from a document element
Suggestion to the documentListen to audioGet a link from a document element
APPENDIX 7
to the Regulation on the procedure for the examination of design solutions for urban planning and design documentation for the construction, reconstruction, overhaul and current repairs of facilities in accordance with urban planning documentation
Suggestion to the documentListen to audioGet a link from a document element
SAMPLE
Suggestion to the documentListen to audioGet a link from a document element
Expert opinion of urban planning documentation
Suggestion to the documentListen to audioGet a link from a document element
Suggestion to the documentListen to audioGet a link from a document element

On company letterhead

EDS (director)

CONSOLIDATED EXPERT OPINION #______

construction, reconstruction, maintenance and overhaul of the facility according to the working project

«_________________________________________»
(name of the construction object according to the design assignment)

Customer: ____________________________________ Chief designer: _________________________________ License # __, «__» ___________________________ (when issued, by whom)
Source of financing: _______________________
General contractor: _________________________________
(if established by the decision-making body)
Construction type: ___________________________________ (new construction, reconstruction, overhaul, etc.)

I. Basis for design.

1. Decisions of the President of the Republic of Uzbekistan, the Cabinet of Ministers, etc.

2. Approved design assignment (in coordination with the relevant departments and organizations, when and by whom?)

3. When and by whom the architectural and planning assignment was issued

4. Specifications for connection to utility networks and materials for agreement with interested organizations operating engineering networks.

5. Conclusion based on the results of engineering and geological studies of the construction site.

6. Summary of energy efficiency indicators of the facility project.

7. Conclusion on the technical inspection of buildings and structures requiring reconstruction or repair.

8. The contract for design and survey work, “__” ______ 20 ___

9. Defect detection statement approved on “__” ______ 20 ___ by the customer in the specified order.

II. Materials submitted for examination.

The content of the "Working draft or documents" at the stage of project development.

III. Summary of project decisions(content should be concise and clear).

1. Construction site conditions (geology, strength, safety, seismic resistance, fire safety, etc.).

2. Master plan of the facility (main feasibility study indicators, bordering).

3. Location of the construction site.

4. Basic design solutions (in terms of durability, safety (seismic resistance and fire safety) and technical regulations - parameters and indicators of the design of the project (m2, m3)).

IV. Engineering support of the projected object:

Drinking water, electricity, heat supply, sewerage, alarm systems, etc. (compliance with technical requirements in the design and other solutions).

V. Project approval documents.

1. Summary of the customer (whether there is a demand or supply).(талаб ва таклифлар бор ёки йўқлиги).

2. Conclusion of the state ecological expertise.

3. Local architectural authority and other interested agencies.

VI. Examination results.

1. During the examination process, the following main corrections and additions are made to the project documentation based on the comments of the experts.

2. According to the results of the examination, the cost of the project, taking into account value added tax (VAT) and other expenses of the customer in the amount of ____ thousand soums, was reduced by ____ thousand soums and set at ____ thousand soums. In particular:

Construction and installation works: ____ thousand soums.

Tools: ____ thousand soums.

VAT: ____ thousand soums.

Other expenses of the customer: ____ thousand soums.

3. The final cost is determined by the customer and the contractor based on the results of the control measurement after construction is completed.

EDS (staff)

4. Before approving the project documentation, the customer must coordinate it with all interested bodies in the prescribed manner.

5. The customer is responsible for the completeness of the design documents submitted for examination, the accuracy of the information, and the developer is responsible for the design decisions made.

VII. Conclusions.

Taking into account the results of the examination, «_________________________________________»
(name of the construction object according to the design assignment)

this working draft is recommended for further consideration and approval.

Executive Specialist

EDS

(staff)

Full name

_________________

Full name

Participating experts:

_________________
Full name

Suggestion to the documentListen to audioGet a link from a document element
Note:
Suggestion to the documentListen to audioGet a link from a document element
This opinion is of a standard nature, and if there are requirements for some urban planning documents that are not mentioned in this opinion, an opinion on additional requirements should be given to the design documents under consideration without deviating from the requirements of this standard opinion.
Suggestion to the documentListen to audioGet a link from a document element
Suggestion to the documentListen to audioGet a link from a document element
ANNEX 2
to the resolution of Cabinet of Ministers of the Republic of Uzbekistan of September17 , 2021, No. 579
Suggestion to the documentListen to audioGet a link from a document element
List of resolutions of the Government of the Republic of Uzbekistan, recognized as invalid
Suggestion to the documentListen to audioGet a link from a document element
Suggestion to the documentListen to audioGet a link from a document element
1. Resolution #150 of the Cabinet of Ministers of the Republic of Uzbekistan “On approval of the Regulations on the procedure for a differentiated approach in determining the timing and cost of the implementation of procedures for the issuance of permits in the field of construction” dated May 30, 2013 (Link) (National database of legislation of Uzbekistan, 2013, #5, Article 33).
Suggestion to the documentListen to audioGet a link from a document element
2. Resolution of the Cabinet of Ministers #15 dated January 22, 2016 (Link), Appendix #4 – “Regulations on the procedure for organizing and conducting state expertise of urban planning documentation”.(National database of legislation of Uzbekistan, 2016 й., #1, Article #6)
Suggestion to the documentListen to audioGet a link from a document element
3. Paragraph 5 of the Appendix of the Resolution #166 of the Cabinet of Ministers of the Republic of Uzbekistan “On amendments to some decisions of the Government of the Republic of Uzbekistan” (Resolution #15 of the Cabinet of Ministers of the Republic of Uzbekistan “On additional measures to improve design work and expertise of investment projects financed by centralized investments” dated January 22, 2016) dated May 23, 2016 (Link).
Suggestion to the documentListen to audioGet a link from a document element
4. Paragraph 4 of the Resolution #63 of the Cabinet of Ministers of the Republic of Uzbekistan “On additional measures to introduce modern and transparent mechanisms for the provision of land plots and the realization of the right to lifelong inheritable possession of land plots for individual housing construction” Dated January 28, 2019 (Link).
Suggestion to the documentListen to audioGet a link from a document element
5. Paragraph 23 of the Appendix 1 of the Resolution #498 of the Cabinet of Ministers of the Republic of Uzbekistan “On the introduction of amendments and additions, as well as the invalidation of some decisions of the Government of the Republic of Uzbekistan in connection with the radical improvement of the public administration system in the field of construction” dated June 14, 2019 (Link).
Suggestion to the documentListen to audioGet a link from a document element
6. Paragraph 1 of the Appendix of the Resolution #961 of the Cabinet of Ministers of the Republic of Uzbekistan “On amendments to some decisions of the Government of the Republic of Uzbekistan” dated November 28, 2019 (Link).
Suggestion to the documentListen to audioGet a link from a document element
7. Paragraph 122 of the Appendix of the Resolution #1046 of the Cabinet of Ministers of the Republic of Uzbekistan “On amendments to some decisions of the Government of the Republic of Uzbekistan” (Decree -#5723 of the President of the Republic of Uzbekistan “On improving the procedure for determining the amount of wages, pensions and other payments” dated May 21, 2019) dated May 23, 2016 (Link).